Re: Earliest/Latest start - Earliest/Latest finish in master recipe scheduling

$
0
0

Hello Fernando

 

Process orders are generally scheduled both forwards and backwards. The scheduling type defines  which scheduling direction is taken into account first. The dates of the earliest dates result from forward

scheduling. The dates of the latest dates result from backward scheduling. The operation dates are determined from the dates of the respective phases. Here, the min max rule applies, the earliest start and latest finish dates are copied to the operation dates.

 

 

 

For more information please have a look at the consulting notes 156115 and 151503.

 

BR

 

Caetano